During the last 2 weeks in April 2016 and the 1st week of May 2016, we moved to a new factory in Yeovil.  During this time period we required a series of tasks completed to prepare the new factory for our occupancy.

We needed an office built on the mezzanine, which was completed by RG JohnsonRalph and his team built the office within week enabling us to complete the decoration in time for the move.  His staff were efficient, polite and left the factory clean and tidy.

ABM4Electrical, completed all electrical work required over a 2 week period, to fit in with the office build and machine commissioning.  They lowered the factory lights, advised on the correct lighting for the office and fitted a new heater in the office.  Mark and Mike, both worked long days to ensure the power was ready for each machine.

The whole computer network, server, computers and a complete new telephone system was moved and set up in 1 day by AF-ITAndy and his team were also, on hand to correct any issues we had for a couple of days after the install.  Lee and Andy both re visited the factory when an issue was not able to be fixed remotely.

Adam from Adams Locks, the Master Locksmith, changed all our locks, provided and new padlock for the front gate and successfully picked a desk draw lock and supplied a new lock and key for an ink cabinet.

Yellow Box, supplied and fitted new signs for the factory, fitting them around the showers that were frequent on that day.

Without these key suppliers the move to our new factory would not have been possible.  I thank them for their efforts and I could not recommend them highly enough.

Adrian Manning

 